Sahyadri Homes
PROTOTYPESample builder record: names, projects and complaint counts are illustrative.
Delivered 5 projects since 2017: 2 on time, 3 late by 23 months on average. 3 RERA complaints, or 1.2 per 1,000 homes (average across builders: 2.7). 0 projects listed with us now.
Delivery record
| Project | RERA date | Delivered | Result |
|---|---|---|---|
| Cedar Heights Hadapsar, Pune | Dec 2024 | Dec 2027 | 36 mo late |
| Sunrise Heights Baner, Pune | Dec 2024 | Jun 2025 | 6 mo late |
| Harmony Crest Velachery, Chennai | Dec 2021 | Dec 2021 | On time |
| Royal Courtyard Andheri East, Mumbai | Dec 2021 | Feb 2024 | 26 mo late |
| Royal Enclave Kharghar, Mumbai | Dec 2017 | Dec 2017 | On time |
RERA complaints, in context
Complaints per 1,000 homes delivered. 3 complaints in total, 1 resolved. Most are about delays and refunds; read the orders on the portal.
Projects listed now
No projects listed with us right now.
Sample record. Built from RERA registrations, completion certificates and complaint orders, with dates. Last updated 3 Oct 2026. How we compute these →